At 2 o'clock on September 22, 2021, the 55,303 test EMU set off on time from Zhengzhou South Railway Station, marking the start of the new Zhengzhou South Railway Station, and the dynamic verification of the transfer construction on the same site.
The newly-built Zhengzhou South Railway Station is the junction station of Zhengyu High-speed Railway, Zhengfu High-speed Railway, Zhengdengluo Intercity Railway, and Jinan Intercity Railway. The designed scale is 16 platforms and 32 arrival and departure lines, which are divided into Zhengwanchang, Zhengfuchang and Zhengfuchang. Intercity field.
The newly-built Zhengzhou South Railway Station is an important hub station for the M-shaped high-speed railway network in Henan Province and the intercity railway network of the Central Plains urban agglomeration. The total construction scale is 500,000 square meters and the investment is nearly 15 billion yuan. There are 3 floors above the ground, from high to low. The elevated floor, platform floor and ground floor, and the first underground floor is a subway line. The exterior design incorporates the regional cultural elements of "Lotus and Crane Square Pot", creating a new architectural image of "Crane Dance Kyushu".
At present, the overall construction of the Zhengzhou South Railway Station hub has entered the stage of decoration and decoration and electrical and mechanical installation. The elevated floor, platform layer, ground floor, and subway floor have all begun to be internally decorated. The same site transfer construction is the last of the entire Zhengzhou South Railway Station hub construction. A key control point.
After the dynamic verification is completed from September 22 to 29, the same-site transfer construction will enter the preliminary acceptance and safety assessment stage.
Keywords: engineering news, engineering construction information
After the construction of the transfer line on the same site is completed, the original "closed area" of Zhengzhou South Railway Station will be fully constructed. The overall project will fill the last "gap" and enter the final construction stage of the project. Editor/Sang Xiaomei