On January 18, 2022, the Guangxi Zhuang Autonomous Region Public Resource Trading Center issued a tender announcement for the general contracting of the design and construction of the Shangsi to Dongzhong Port section of the Longsheng-Tongzhong Port Highway. The tender unit was Guangxi New Development Transportation Group Co., Ltd. The section from Shangsi to Dongzhong Port of Longsheng-Dongzhong Port Highway is an important part of the "18" expressway in "1 Ring, 12 Horizontal, 13 Vertical and 25 Connections" in the "Guangxi Expressway Network Planning (2018-2030)".
Project Overview
Main line: It starts from the original seven-gate single-horn interchange on the Hepu-Napo Expressway in the west of Shangsi County, and transforms the original Seven-gate Interchange into the Shangsi West Hub Interchange to connect the Hepu-Napo Expressway. The route goes south through Shangsi. County Siyang Town, Callan Town, Hualan Town, Pingfu Township, Nanping Yao Nationality Township, Ningming County Nanan Township, and finally at the main line toll station in Dongzhong Town, Fangcheng District, and connect to the main line connection line. The total length of the route is 83.5km. It adopts the standard of two-way four-lane expressway. The design speed is 100km/h and the width of the roadbed is 26m. Set up 19,809.5m/44 bridges (excluding main line bridges, including 4,828m/4 extra large bridges, 15,085m/38 bridges, 457.5m/6 small and medium bridges), 65 culverts (excluding main line), and 19,443m tunnels /12 (including 8859m/2 extra-long tunnels, 5 long tunnels 7411.5m/5, and 3172.5m/5 short and medium tunnels), 4 interchanges (including 1 hub interchange), 10 separate interchanges, channels 56 roads (excluding the main line of communication), 2 service areas, 1 parking area, 1 main line toll station, 4 ramp toll stations, 2 maintenance work areas, 1 monitoring and communication sub-center, and 2 tunnel management stations.
Main line connecting line: The starting point is connected to the main line, and it ends near Tongsha in Tongzhong Town, and then connects to Nasha Avenue planned by Tongzhong Town. The total length of the route is 0.839km, adopting the first-class highway standard, the design speed is 80km/h, and the roadbed width is 25.5m. Set up 4 culverts and 1 plane intersection.
Shiwandashan connecting line: the total length of the line is 14.908km, and it adopts the second-class highway standard, the design speed is 60km/h, and the roadbed width is 10m. Set up 288m/2 bridges, 34 culverts, and 2 plane crossings.
Dongzhong connecting line: The total length of the route is 2.221km, and it adopts the second-class highway standard, the design speed is 60km/h, and the roadbed width is 10m. Set up 220m/1 bridge, 7 culverts and 2 plane intersections.
Changdun connecting line: the total length of the line is 5.745km, and it adopts the second-class highway standard, the design speed is 60km/h, and the width of the roadbed is 8.5m. Set up a bridge of 188.5m/1, 15 culverts, and 2 plane crossings.
Bidding scope
The scope of this bidding is for the main line K0+000~K83+500, the main line connecting line K83+500~K84+339.925, the Shiwandashan connecting line LK0+000~LK14+908.125, and the Dongzhong connecting line PK0+000~PK2 +221.44 section and Changdun connecting line QK0+000~QK5+742.288 construction drawing survey and design and the general contracting of the corresponding engineering construction, set up 1 bidding section (No. 1). The specific contents are: road engineering (including routes, subgrades, pavements, bridges and culverts, tunnels, intersection projects, etc.), traffic engineering and facilities along the line (including safety facilities, greening, housing construction, water conservation, environmental protection, electromechanical), etc. Determination ( Including supplementary survey) detailed survey work, construction drawing design, budget preparation, project engineering quantity list and project-specific technical specification preparation, engineering construction and defect repair, etc.
The design and construction general contracting period of this project is 36 months, 1080 calendar days, of which the construction drawing design period is 6 months, 180 calendar days, which will be calculated from the time specified in the work start notice issued by the contractor or supervisor duration.
Obtaining and submitting tender documents
Anyone who intends to participate in the bidding, please log in to the public resources electronic trading platform of Guangxi Zhuang Autonomous Region from 2022-01-18 to 2022-01-25 by the full-time bidder of the potential bidder with the unit account number and password or enterprise CA lock to download the bidding documents for free. .
The bidding documents include encrypted electronic bidding documents and non-encrypted electronic bidding documents. The deadline for submitting bidding documents (bidding deadline, the same below) is 10:00 on March 21, 2022. Bidders should submit their bidding documents in the following two ways before the bidding deadline: (1) Online submission: Bidding Before the deadline for bidding, the person should use the CA digital certificate to log in to the "public resource trading platform" of Guangxi Zhuang Autonomous Region through the Internet, upload the encrypted electronic bidding document, and save the electronic receipt certificate automatically generated by the system after the upload is successful. The submission time is Electronic receipt voucher time. (2) On-site submission: The bidder shall, before the deadline for bidding, seal and mark the unencrypted electronic bidding documents according to the requirements of the bidding documents, and submit them to the Guangxi Zhuang Autonomous Region Public Resource Trading Center on the 4th floor of the Guangxi Zhuang Autonomous Region Government Affairs Service Center. (No. 6, Yibin Road, Qingxiu District, Nanning City) Public bid opening (the specific bid opening room is arranged according to the electronic screen display). Editor/Sang Xiaomei
Comment
Write something~