Jiangxi Daguang Expressway Xiaoyuan Tunnel Completed
Seetao 2022-06-13 14:19
  • The Xiaoyuan Tunnel is 390 meters long, with a maximum excavation cross-sectional area of 270 square meters
Reading this article requires
3 Minute

On June 10, 2022, the Xiaoyuan Tunnel of the reconstruction and expansion project of the Ji'an-Nankang section of the Daguang Expressway was successfully completed after 252 days of intense construction.

As the first single-hole four-lane construction project of Jiangxi Expressway, Xiaoyuan Tunnel is a controlled project of the whole line, with a total length of 390 meters, a net height of 5 meters, a net width of 18.25 meters, and an excavation area of 275.7 square meters. The project adopts the construction technology of double-sided guide pit + double-layer arch frame to divide the super large section into multiple small sections for excavation and support.

The reconstruction and expansion project of the Ji’an-Nankang section of the Daguang Expressway is an important part of the G45 Daqing-Guangzhou Expressway of the National Expressway Vertical Line 5, and it is the most important north-south channel of the expressway network in Jiangxi Province.Editor/Ma Xue

Comment

Related articles

Construction

The construction boom of key projects in the west of Xingtai is surging

01-07

Construction

Shanghai's billion dollar North South Passage starts construction

01-05

Construction

The construction of the Mengxi-Beijing-Tianjin-Hebei ±800 KV UHV project has commenced

01-04

Construction

Shanghai deployed to promote high-quality construction of the the Belt and Road

01-04

Construction

Crossing 2681 kilometers in 0.009 seconds, another 'super project' has arrived!

09-19

Construction

Zhoushan 500kV project strengthens China's energy artery

09-18

Collect
Comment
Share

Retrieve password

Get verification code
Sure