Photovoltaic
Jiangsu Agriculture and Solar Hybrid Power Generation Project won the bid
Seetao 2022-06-20 14:27
  • The Huai'an District project has a total installed capacity of 585MW and a planned construction period of 426 calendar days
  • The total installed capacity of the agricultural-optical hybrid power generation project in Shiliu Street, Donghai County is 490MW, with a planned construction period of 426 calendar days
Reading this article requires
5 Minute

On June 18, 2022, the China Bidding Public Service Platform released the announcement of the winning candidates for the EPC general contracting of the agricultural-photovoltaic hybrid power generation project in Fanji Town, Huai'an District, and the announcement of the winning candidates for the EPC general contracting of the agricultural and solar hybrid power generation project in Shiliu Street, Donghai County. Both projects were won by Beijing Tianyuan Kechuang Wind Power Technology Co., Ltd., with a total investment of over 4.4 billion yuan for the two projects.

Agriculture-Solar Hybrid Power Generation Project in Fanji Town, Huaian District

The project is located in Zhaxi Village, Fanji Town, Huaian District, Huaian City, Jiangsu Province. The total installed capacity is 585MW, all of which are installed by fixed brackets. The photovoltaic power station is equipped with 35 sets of 1250KVA transformers and 70 sets of 630KW inverters. Total planned duration: 426 calendar days.

Bidding Information

Beijing Tianyuan Kechuang Wind Power Technology Co., Ltd. won the first bid for the project, with a bid price of 2.16 billion yuan.

Donghai County Shiliu Street Agriculture-Solar Hybrid Power Generation Project

The project is located in Mawang Village and Liuwang Village, Shiliu Street Office, Donghai County, Lianyungang City, Jiangsu Province. The total installed capacity is 490MW, all of which are installed by fixed brackets. The photovoltaic power station is equipped with 39 sets of 1250KVA transformers and 78 sets of 630KW inverters. Total planned duration: 426 calendar days. Keywords: engineering news, engineering construction, engineering construction information

Bidding Information

Beijing Tianyuan Kechuang Wind Power Technology Co., Ltd. was the first candidate to win the bid for this project, with a bid price of 2.3 billion yuan. Editor / Zhao E

Comment

Related articles

Photovoltaic

Israel builds photovoltaics in the occupied Palestinian territories

11-26

Photovoltaic

Xianna Optoelectronics and American Grape Solar signed a strategic cooperation agreement

11-26

Photovoltaic

Longyuan Power 150MW photovoltaic project was filed

10-17

Photovoltaic

Mechanical completion of JTC PV project in Jurong Island, Singapore

10-14

Photovoltaic

5GW! Indonesia's largest integrated photovoltaic manufacturing project starts construction

10-11

Photovoltaic

India will add new PV capacit

10-10

Collect
Comment
Share

Retrieve password

Get verification code
Sure