  • Jiangyin Jingjiang Yangtze River Tunnel South Line is 11.405 kilometers long, with a design speed of 100 kilometers per hour
  • The Wuxi section of the Huwu Expressway expansion project is about 33 kilometers long, and the preliminary design of the project has been approved
Reading this article requires
12 Minute

On August 1, 2022, the Wuxi Municipal Government of Jiangsu Province held a meeting to promote the construction of key transportation and livelihood projects. It was mentioned at the meeting that in 2022, Wuxi City will strive to realize the expansion of Xiyi Expressway, Xitai Expressway, Jiangyin Jingjiang Yangtze River Tunnel South Connection, The construction of four expressways including the expansion of the Jiangyin pilot section of the Shanghai-Wuhan Expressway has started, and the pace of the four-way joint construction is accelerating.

Xiyi Expressway Expansion Project

The Wuxi-Yixing Expressway Expansion Project will initially implement a section of about 36 kilometers from Xueyan Junction to Xiwu Junction. The preliminary design has been approved by the Provincial Development and Reform Commission, and the relocation of houses within the main line of the Yixing section has been basically completed, and the construction drawing design is being advanced. At the same time, speed up the preliminary work of the section from Wuxi North Hub to Xueyan Hub, and actively implement relevant construction conditions.

The route of the expansion section starts from the north side of Xueyan Junction, which intersects with Suxi-Changnan Expressway, Wujin District and Yixing City, Changzhou City, and ends at Xiwu Junction, which intersects with Nanjing-Hangzhou Expressway. The whole line is expanded according to the standard of two-way eight-lane expressway, and adopts the overall expansion plan of widening along both sides of the original road. The width of the roadbed is 42 meters and the design speed is 120 kilometers per hour.

The expansion of the project is of great significance for improving the service capacity of the expressway network, ensuring the safe and smooth operation of the road network, strengthening the connection between Wuxi, Changzhou and Yixing, and promoting the regional integration of the Yangtze River Delta and the development of the Suzhou-Six-Changzhou metropolitan area.

Yixing service area renderings

Xitai Expressway Project

The Wuxi-Taicang Expressway project has a total length of about 50 kilometers, of which the Wuxi section is 31.7 kilometers. At present, the preliminary design is being carried out, and the pipeline relocation and greening relocation are simultaneously promoted.

After the project is completed, it will become one of the main roads in southern Jiangsu, which will greatly relieve the traffic pressure on the Shanghai-Nanjing expressway, and at the same time make the connection between Wuxi and Suzhou smoother, and will promote the formation of a new urban development convergence axis and a new transportation corridor.

Wangyu River Bridge renderings

Jiangyin Jingjiang Yangtze River Tunnel South Line

In July 2022, the preliminary design of the Jiangyin Jingjiang Yangtze River Tunnel South Link Project was approved by the Provincial Development and Reform Commission, which is another major progress after the approval of the project feasibility study in January 2022, laying a solid foundation for the start of construction within the year .

The south connection of Jiangyin Jingjiang Yangtze River Tunnel is an important supporting project of the Jiangyin Jingjiang Yangtze River Tunnel currently under construction. It starts from Jiangyin Furong Avenue, connects with Jiangyin Jingjiang Yangtze River Tunnel, and uses the planned corridor from the starting point to the Nanyun section, ending at the intersection with Huwu Expressway. It is connected to Xuxiake Avenue, with a total length of 11.405 kilometers. The whole line adopts the construction standard of two-way six-lane expressway, the total width of the roadbed is 33.5 meters, and the design speed is 100 kilometers per hour.

After the project is completed, it will greatly ease the traffic pressure of Jiangyin Bridge and relieve congestion. At the same time, it is of great significance to implement the integration of the Yangtze River Delta, improve the regional expressway network, promote the cross-river integration of the Xichangtai group and the integrated development of Chengjing.

South Gate Interconnection Effect Map

Xu Xiake intercommunication renderings

Jiangyin Pilot Section of Huwu Expressway Expansion Project

The expansion project of the Taicang-Changzhou section of the Shanghai-Wuwu Expressway has a total length of 134.865 kilometers, of which the Wuxi section is about 33 kilometers long. The preliminary design of the project has been approved by the Ministry of Transport, and the construction drawings of the pilot section have been reviewed by the Provincial Communications Construction Bureau. Key words: engineering construction information, engineering construction, engineering news

The expansion of the project has a positive effect on implementing the integrated development strategy of the Yangtze River Delta, improving the traffic capacity and service level of the national expressway, strengthening the inter-city connection in southern Jiangsu, and promoting the coordinated economic and social development of the regions along the route. The four-way joint construction will create a demonstration area for the modernization of transportation in Wuxi, injecting strong momentum, looking forward to it! Editor/Zhao E

Comment

Related articles

Transportation

Road Construction holds 2024 New Quality Development Technology Seminar

11-26

Transportation

Shanghai Zhoudeng Expressway officially starts construction

10-15

Transportation

The terminal building of Dalian New Airport has started construction!

10-14

Transportation

70 billion yuan intercity railway project is coming!

10-14

Transportation

Seymour is about to build a road

10-12

Transportation

The Kazakhstan Mongolia highway connection is about to be launched

10-12

Collect
Comment
Share

Retrieve password

Get verification code
Sure