On August 30, 2022, shortly after the project feasibility study was approved, the tender announcement for the review of construction drawings of the new Nantong-Ningbo high-speed railway was released at the Nanjing Public Resources Trading Center. The project has been approved by the National Development and Reform Commission with the approval of the National Development and Reform Commission on the feasibility study report on the new Nantong-Ningbo high-speed railway. The project owner is Shanghai-Hangzhou Railway Passenger Dedicated Line Co., Ltd.
Project Overview
The new Nantong-Ningbo high-speed railway line starts from Yancheng to Nantong West Station of Nantong High-speed Railway, passes through Zhangjiagang City, Changshu City, Suzhou City in Jiangsu Province, Jiaxing City and Ningbo City in Zhejiang Province, and finally ends at Ningbo Hub, Ningbo Station.
The total length of the line is about 309.8 kilometers, including 300.7 kilometers of new lines, 9.1 kilometers of existing lines, and 10 stations. A new double-track railway bridge across Hangzhou Bay will be built. Simultaneously build the Jiaxing South Railway Station Shanghai-Kunming Line, the line and the Xiaoyong Line, the Suzhou North Railway Station and the parking lot, expand the Ningbo Railway Station, and reserve the construction land for the Jiaxing South Railway Station. The total project duration is 5 years.
The planned construction period of this tender section: from the date of signing the contract until the project passes the completion acceptance.
Main technical standards
Rail class: high-speed rail. Number of positive lines: double lines. Design speed: 350 km/h. Maximum slope: 20‰ for general sections and 25‰ for difficult sections. Minimum curve radius: 7,000 meters for general areas and 5,500 meters for difficult areas. The effective length of the arrival and departure line: 650 meters. Traction type: Electric. Train operation control mode: CTCS-3 train control system. Dispatch command method: dispatch centralized. Other technical standards implement high-speed railway design specifications. Key words: engineering construction information, engineering news, engineering construction
Tender division
This tender is divided into 2 sections, namely TYSS-1 bid: Nantong West YTDK160+000 to DK96+203; TYSS-2 bid: DK96+203 to DK271+905.
Bid Deadline
The time for submitting bidding documents is from 9:00 to 9:30 on September 27, 2022, and the deadline for submitting bidding documents is 9:30 on September 27, 2022. The location is: designated by the North Gate of Nanjing Public Resources Trading Center area. Editor/Zhao E