On September 1, 2022, the bidding announcement for the unit price contracting of the construction of the new Xiangyang-Jingmen high-speed railway station front project was released. The project has been approved for construction by China National Railway Group Co., Ltd. and the Hubei Provincial People's Government, with a total investment of 18.832 billion yuan. It marks that the Xiangyang-Jingmen section of the Hunan high-speed railway is about to enter the formal construction stage.
Project Overview
The construction site of this project is located in Hubei Province.
Construction scale: The newly built Xiangyang-Jingmen high-speed railway will lead from Xiangyang East Station and go south through Yicheng to Jingmen West Station of Shanghai-Chongqing High-speed Railway along the Yangtze River. The new line is 116.23 kilometers long.
The whole line has 4 stations in Xiangyang East, Yicheng North, Shuanghe West and Jingmen West, as well as 2 line stations including Qiangang and Guolou. Among them, Xiangyang East is an existing station, Yicheng North and Shuanghe West are newly built stations, and Jingmen West is a station under construction. Design speed: 350 km/h.
Bidding scope and division of tenders
The bidding for the construction of the new Xiangyang-Jingmen high-speed railway station front project is divided into four tender sections: XJZQ-1 tender, XJZQ-2 tender, XJZQ-3 tender, and XJZQ-4 tender. The project content includes all the construction drawing design contents of the tender section.
Division of tenders: This tender is divided into 4 tenders:
XJZQ-1 mileage/range: DK0+000~DK6+438.05 section of main line and tie line project, including DK0+000~DK6+438.05, YDK0+000~YDK6+452.862, LZDK0+000~LZDK6+442.34, LSDK0+122.04 ~LSDK1+008.79, LXDK0+122.0~LXDK0+892.82, ADK0+000~ADK0+195 online track project, excluding track laying, base, ballast, etc.; DK6+438.05~DK30+678.15.
XJZQ-2 mileage/range: DK30+678.15~DK57+856.96.
XJZQ-3 mileage/range: DK57+856.96~DK87+960.70.
XJZQ-4 mileage/range: DK87+960.70~DK117+070.38.
Planned construction period: 1277 calendar days, planned start date: October 30, 2022, and planned completion date: April 29, 2026. Key words: engineering construction information, engineering news, engineering construction
Acquisition and submission of tender documents
Bidders are requested to log in to the Beijing Engineering Construction Public Resources Trading Platform from 17:00 on September 1, 2022 to 17:00 on September 6, 2022 to download the electronic bidding documents. The submission time of the bidding documents is from 09:00 on September 23, 2022 to 10:00 on September 23, 2022, and the deadline is 10:00 on September 23, 2022. The location is: Beijing construction project contracting Bid opening area of contract trading center. Editor/Zhao E