Transportation
Xining-Chengdu Railway Ganqing Section Station Front Project XCTJ1-13 Bidding
Seetao 2022-09-15 09:19
  • The total length of the project route is 498.9 kilometers, with a total investment of 83.15 billion yuan
  • The project is scheduled to start construction at the end of October, with a total construction period of 7 years
Reading this article requires
7 Minute

Recently, the bidding announcement for the unit price contracting of the construction of the XCTJ1-13 tender section of the Ganqing section of the newly built Xining-Chengdu railway was released. The project is scheduled to start construction at the end of October, with a total construction period of 7 years.

The Xining-Huangshengguan section of the newly built Xining-Chengdu Railway has a total length of 498.9 kilometers and a total investment of 83.15 billion yuan.

Project Overview

The construction sites of this project are located in Gansu Province, Qinghai Province and Sichuan Province.

Construction scale: The Xining-Chengdu Railway Xining-Huangshengguan section Ganqing section is newly built, with a main line of 329.9km in length, a class I double-track railway, and a bridge-to-tunnel ratio of 90.8% for the main line. The length of the main bridge is 59.808km/92; the length of the main tunnel is 236.44km/51, including related projects introduced into Xining area.

The design speed of the passenger train is 200km/h, and some road sections are reserved to increase the speed to 250km/h on the plane condition.

Bidding scope

All temporary land, subgrades, bridges, tunnels, tracks, production and living houses, platform canopies and foundations, other operating production equipment and buildings, Dalin Project and other related projects within the range of DK177+150-DK532+300 of the Gansu-Qingdao section of the Xicheng Railway .

Excluding the station building and related projects within the design scope of the station building, four electricity and information customer service, disaster prevention subsystem engineering, tunnel lighting, etc., excluding Xining EMU and driving apartments, Xining Locomotive Depot, etc. entrusted by Qinghai-Tibet Company for construction project.

This tender is divided into 13 sections, including 8 sections in Gansu Province, the XCTJ1 bid is about 3.9km located in Sichuan Province, and 5 sections in Qinghai Province, excluding the Gansu-Qingdao Tunnel that has been started in advance and the east-west entrance of the sea. For the project, the lot numbers are XCTJ1~13. Keywords: engineering news, engineering construction information, engineering construction

Planned Duration

The planned start date of this project is October 26, 2022, and the planned completion date is October 25, 2029, of which:

Tang Gaang to the cooperation section: 1876 calendar days, the planned start date is October 26, 2022, and the planned completion date is December 15, 2027.

Cooperation to Langmusi section: 2191 calendar days, the planned start date is October 26, 2022, and the planned completion date is October 25, 2028.

Haidongxi to Tanggaang section: 2556 calendar days, the planned start date is October 26, 2022, and the planned completion date is October 25, 2029.

Online bid opening time: 10:00 on September 20, 2022, bid opening location: the eighth bid opening hall on the sixth floor of Gansu Public Resources Trading Center.Editor/Zhao E

Comment

Related articles

Transportation

Shanghai Zhoudeng Expressway officially starts construction

10-15

Transportation

The terminal building of Dalian New Airport has started construction!

10-14

Transportation

70 billion yuan intercity railway project is coming!

10-14

Transportation

Seymour is about to build a road

10-12

Transportation

The Kazakhstan Mongolia highway connection is about to be launched

10-12

Transportation

Jiangsu Changzhou Metro Line 6 starts construction

10-07

Collect
Comment
Share

Retrieve password

Get verification code
Sure