On September 24, 2022, the successful bidders for the construction of the total price contract for the construction of the Chengdu-Yingshan section of the newly built Chengdu-Dazhou-Wanzhou Railway were announced and released. The Chengdawan high-speed railway project will officially start construction in October, with a planned construction period of 5 years and a total project investment of about 21 billion yuan.
Project Overview
The construction sites of this project are located in Ziyang City, Suining City and Nanchong City.
Construction Scale: The project started from the Chengdu hub and was built from the Tianfu Railway Station. After using the Chengdu Railway to Ziyang West Railway Station, the new line will pass through Ziyang City, Suining City, Nanchong City, Dazhou City in Sichuan Province and Kaizhou District and Wanzhou District in Chongqing City. , access to the existing Wanzhou North Station.
The total length of the line is 486.4 kilometers, including 432.4 kilometers of new railways and 54 kilometers of railways under construction. There are 13 stations on the whole line, including 7 new stations. Supporting the expansion of the Tianfu EMU application station, the reconstruction of the existing 15.4-kilometer railway line, and the newly built 4-kilometer Sui railway connecting line and other related projects. Design speed: 350 km/h.
The planned construction period is 5 years, the planned start date is October 1, 2022, and the planned completion date is September 30, 2027.
Tender division and bid winning candidates
Scope of bidding: The project in front of the station from Chengdu to Yingshan (D2K463+545.8~DK211+772.700) (excluding prefabrication of double-block sleepers and track laying), the line length is 220.356km.
This tender is divided into 8 tenders
CDWZQ-2, the number of projects is: 24 main bridges/11.794km; 25 roadbeds/6.191km; 3 tunnels/1.056km; 354 holes for the frame; 31.625km for transportation and installation of double-block ballastless beds and sleepers. The key control projects are: Ziyang Tuojiang Bridge, Lanjiawan Bridge, Renjiawan Bridge, Zengjiawan 1# Bridge.
Mileage/range: main line D2K444+505~D2K463+545.8, main line length 19.041km; right line detour section: D2K460+984.066~D2YK463+536.382, detour section length 2.552km.The first winning candidate for this tender section: China Railway Bridge Bureau Group Co., Ltd., the bid price: 2.188 billion yuan.
CDWZQ-3, the number of projects is: 43 bridges/16.441km; 44 roadbeds/13.248km; box girder frame 394 holes; double-block ballastless ballast bed and sleeper transportation and installation 60.379 km. The key control projects are: Zhanlingshan Bridge, Jinma Village Bridge, Dishuiyan Reservoir Bridge. Mileage/range: D1K404+969.65~D2K444+505, the main line length is 29.626km.
The first winning candidate in this bidding section: China Railway Second Bureau Group Co., Ltd., the bid price: 2.265 billion yuan.
CDWZQ-4, the number of works is: 31 bridges/20.796km; 34 roadbeds/8.484km; 6 tunnels/2.535km; box girder frame 584 holes; double-block ballastless track bed and sleeper transportation and installation 64.619km; station : Lezhi Station; pouring of ballastless track bed and turnout installation and commissioning in turnout area. The key control projects are: the extra-large bridge across Suihong Expressway, the Baotou Reservoir Bridge, and the extra-large Lezhi station bridge. Mileage/range: DK367+795.350~DK404+969.65, the main line length is 31.816km.
The first winning candidate for this tender section: China Railway Shanghai Engineering Bureau Group Co., Ltd., the bid price: 3.027 billion yuan.
CDWZQ-5, the number of projects is: 41 bridges/19.949km; 49 roadbeds/10.059km; 11 tunnels/2.585km; 107 holes of box girder frame and bridge deck system; transportation and installation of double-block ballastless ballast bed and sleepers in this bid section and Suicheng tie line, DK330+000~DK335+213.831 section; 74.716km for ballastless ballast bed pouring and turnout in turnout area Installation and commissioning. The key control projects are: Cross-Sui-Nei Expressway Super Bridge, Degong Village Super Bridge, Bai'an River Super Bridge, and Mazitan Reservoir Bridge. Involved in the construction of business lines: Suining Station, Degong Village Bridge. Mileage/range: DK335+213.831~DK367+795.350, main line length 32.589km.
The first winning candidate in this bidding section: China Construction Eighth Engineering Bureau Co., Ltd., the bidding price: 2.859 billion yuan.
CDWZQ-6, the number of projects is: 34 bridges/18.139km; 40 roadbeds/5.337km; 22 tunnels/6.399km; Standard box girder frame with 57 holes and bridge deck system, 51 holes of cast-in-situ box girder at large mileage end of Fujiang Extra-large Bridge; transportation and installation of double-block ballastless ballast bed and sleepers for this bid section and section DK313+965.36~DK314+069.063 61.472km ; Station: Pengxi South Station; pouring of ballastless track bed and turnout installation and commissioning in turnout area. The key control projects are: Suining Fujiang Super Bridge, Ma'an Village Cross-Mian Sui Expressway Super Bridge, Damiangou Reservoir Super Bridge, Daxing Township Cross-Hu-Rong Expressway Super Bridge. Mileage/range: DK284+090.830~DK313+965.360, main line length 29.875km.
The first bidder in this bidding section: China Railway Seventeenth Bureau Group Co., Ltd. bidding price: 3.586 billion yuan.
CDWZQ-7, the number of projects is: 26 bridges/9.498km; 27 roadbeds/5.650km; 14 tunnels/13.055km; double-block ballastless ballast bed and sleeper transportation and installation 56.406km. The key control projects are: Jiangjiashan Xihe Bridge, Hejiawan Cross-Mulaoganqu Bridge, Zitongmiaohe Bridge, Datong Town Cross-Daily Railway Bridge, Huangjiashan Tunnel and Damushan Tunnel. Involved in the construction of the business line: Datong Town Cross-Da Railway Extraordinary Bridge. Mileage/range: DK255+887.970~DK284+090.830, the main line length is 28.203km.
The first candidate for the winning bid in this bidding section: China Railway 12th Bureau Group Co., Ltd., the bid price: 2.581 billion yuan.
CDWZQ-8, the number of works: Main line: 7 bridges/10.387km; 10 subgrades/1.926km; 3 tunnels/2.201km; CDWZQ-7 standard box girder frame with 211 holes and bridge deck system; this tender section and DK251+292.18~DK253+800 double-block ballastless ballast bed and sleeper transportation and installation 37.043 km; ballastless ballast bed pouring and turnout installation in the fork area with debugging. The key control projects are: Nanchong Jialing River Super Bridge, Qujiamiao Village Cross-Gaonan Railway Super Bridge, Mozishi Village Luxi River Super Bridge, and Erbaoshan Tunnel. Involved in the construction of business lines: Nanchong North Station, Qujiamiao Village Cross-Gaonan Railway Super Bridge, Mozishi Village Luxi River Super Bridge. Mileage/range: DK238+870.01~DK251+292.18, DK253+800~DK255+887.970, main line length 14.51km.
The first winning candidate for this tender section: Sichuan Highway and Bridge Construction Group Co., Ltd., the bid price: 2.096 billion yuan.
CDWZQ-9, the number of works is: main line: 32 bridges/12.241km; 42 subgrades/8.013km; 12 tunnels/6.555km; CDWZQ-8 standard Nanchong Jialingjiang Bridge box girder frame with 4 holes; double-block ballastless ballast bed and sleeper transportation and installation 53.618km. The key control projects are: Yanshan Village Cross-Yanshan Avenue Super Bridge, Huanghua Village Heshu River Super Bridge, Chuanzumiao Reservoir Bridge, Shuanggongqiao Village Super Bridge, and Yanshanzhai Tunnel. Mileage/range: DK211+772.700~DK238+870.01, main line length 26.809km. Key words: engineering construction information, engineering news, engineering construction
The first winning candidate for this tender section: China Railway Third Bureau Group Co., Ltd., the bid price: 2.463 billion yuan. Editor/Zhao E