Business promotion
Liangzhou Jiuduntan 50 MW photovoltaic project through acceptance
Seetao 2022-10-08 17:10
  • The project acceptance marks that the project has entered the stage of main structure construction and equipment installation
Reading this article requires
5 Minute

Liangzhou Jiuduntan 50 MW PV project successfully passed the first quality inspection and acceptance of the expert group of the renewable energy power generation Engineering Quality Supervision Station on September 20, 2022, marking that the project has entered the stage of main structure construction and equipment installation.

At the acceptance meeting, representatives of the project design unit, supervision unit, general contractor and construction unit reported the progress of the project in turn. The expert group arranged and deployed the inspection project, inspected the construction site and materials of each participating unit carefully, and put forward rectification suggestions and suggestions. Panel to various contractors work gave a high praise, agree that the liangzhou nine pier beach 50 mw photovoltaic projects all the contractors quality supervision system, safety supervision system, management system has been established, and the normal operation, personnel and all kinds of instruments, such as meet the needs of the present management and construction, at the same time, also puts forward constructive Suggestions on site construction of deficiencies, The participating units are required to seriously implement the quality management, safety management and other systems in the construction process, strengthen the project acceptance, process control, strictly implement the project construction standards, to ensure the project quality and safety, stable and controllable.

The next step, the company will according to the expert opinion, the existing problems in the implementation of the rectification, earnestly ensure the closed-loop management, firmly establish a high level to create high quality project management concept, strengthening quality process control, strict quality management throughout the design, procurement, construction, commissioning and production process, to merit, promoting management, quality management implementation project overall merit, Go all out to push the project into production as planned and with high quality. Editor/Zhao E

Comment

Related articles

Business promotion

MLM quadruped robot achieves complex operations while moving

12-11

Business promotion

213 company passed the qualification certification audit for CRRC level suppliers

12-11

Business promotion

Aluminum Breakthrough: Bofa Project Ships 20 Million Tons in Single Year

12-08

Business promotion

Shandong Heavy Industry Weichai Group 2026 Business Conference

12-08

Business promotion

Lumos Robotics Completes Pre-A1 and Pre-A2 Round of Financing

12-08

Business promotion

Leaders from the Yangtze River Maritime Safety Administration and others visited CORNEX

12-06

Collect
Comment
Share

Retrieve password

Get verification code
Sure