The Anhui section of the Shanghai-Nanjing-Hefei high-speed railway won the bid
Seetao 2022-10-11 14:49
  • The new line length of the project is 103.001km, and the target speed is 350km/h
  • The total construction period of the project is planned to be 5 years, with the planned start date in October 2022 and the planned completion date in September 2027
Reading this article requires
12 Minute

On Oct 10, 2022, the bid-winning candidate announcement for the construction and supervision of the pre-station project of the Anhui section of the new Shanghai-Nanjing-Hefei high-speed Railway, the pre-station project of Hefei Hub Station and related supporting works was released. Construction of the Anhui section of the Shanghai-Chongdu-Rong high-speed railway along the northern Yangtze River will begin in October, with a planned construction period of five years.

Description of project

New Shanghai-Nanjing-Hefei high-speed railway Anhui section: Jiangsu and Anhui province boundary to the south of Hefei, mileage range: DK427+948.09 ~ Henning K460+579, line length 130.88km, including 103.001km new line length, the length of the existing line 27.879km. Among them, the bridge project is 85.06km long, the tunnel project is 6.47km long, the bridge and tunnel account for 88.86%, and the existing cable is 27.88km.

Two new stations, Chuzhou Station and Dashu Station, respectively covering 39,000 square meters and 5,000 square meters, respectively.

Main technical standards: Railway grade: high-speed railway; Speed target value: 350km/h; The newly built contact line between the Henning Railway and the Shanghai-Chongyu-rong high-speed Railway and the contact line between Feidong and Hefei Station are designed at 160km/h.

Total duration of the project: 5 years. The planned start date is October 2022 and the planned completion date is September 2027.

The bidding scope

The scope of the tender is for all the station front and fourth power integration and related works within the design scope of the construction drawing of the main line of the Shanghai-Ninghe high-speed Railway Anhui section.

Hefei Hub Project Construction Headquarters of China Railway Shanghai Bureau Group Co., LTD is responsible for the construction of Hefei Hub Project.

Detail plan of Anhui section of Shanghai-Chongdu-Rong high-speed Railway

Division of bidding section and winning candidate

HNZQ-1 standard: from the provincial boundary to Erlang Reservoir Bridge, the total length of the route is 27.101km, including 3.049km of roadbed and 5 Bridges /24.052km. Including Chuzhou Station, the Overpass bridge over Beijing-Shanghai high-speed Railway, the Middle bridge over Rulin Road, the middle bridge over Yongle Road, the Great bridge over Fengle Avenue, Erlang Reservoir Bridge, Beam Yard No. 01, etc.

Name of the proposed winning bidder: China Railway First Inning Group Co., LTD. Median price: 2.395 billion yuan.

HNZQ-2 standard: The total length of the route from Erlang Reservoir Bridge to Chuangmachang Shuikute Bridge is 27.411km, including 3.575km of roadbed, 17.368km of 10 Bridges and 6.467km of tunnel. Including Erlang Tunnel, Shangshiba Reservoir BRIDGE, TRANS-West Ring Highway bridge, TRANS-Xianghe Bridge, Fengshan Tunnel, Trans-Machang Shuikute Bridge and so on.

Name of the proposed bidder: China Railway 14th Bureau Group Co., LTD., bid price: 2.154 billion yuan.

HNZQ-3 standard: The total length of the line is 25.686km from Shuikute Bridge across Machang to Shanghai-Shaanxi Expressway bridge, including 3.288km of roadbed and 22.398km of bridge. Including Dashu station, Shanghai-Shaanxi Expressway bridge, No. 02 beam field.

Name of the proposed winning bidder: China Railway Eighth Bureau Group Co., LTD., bid price: 2.138 billion yuan

HNZQ-4 standard: The total length of the line is 22.115km from Shanghai-Shaanxi Expressway Bridge to Feidong Bridge, including 0.877km of roadbed and 21.238km of 3 Bridges. Including NANYINGzhuang Super BRIDGE, NANYINGZHUANG MIDDLE BRIDGE, FEIDONG SUPER BRIDGE, No. 03 BEAM FIELD, TRACK laying project, etc.

Name of the proposed winning bidder: China Railway Construction Bridge Engineering Bureau Group Co., LTD., bid price: 1.868 billion yuan.

HNHFSNZQ standard: Hefei hub station and related supporting works, including the main line DK530+454.31 ~ K432+700 civil construction, Su-Wan province boundary DK427+948.09 ~ DK530+454.31 rail laying, also built the detour line of Hening, the link line of Hening to the Yangtze River, the third and fourth line of Feidong along the river, and the link line of Hening to Sanshilipu. The roadbed is 10.202 kilometers long, the bridge is 12.187 kilometers long, there are 3 beam fields and 1 track-laying base.

Number of major projects: subgrade earthwork of 2,226,000 cubic meters, 11 general large Bridges of 20.964km, 6 Bridges of 0.639km, frame Bridges of 6,801 square meters, culverts of 1,528 meters, track laying of 273km, ballast laying of 125,000 cubic meters.

Name of the proposed winning bidder: China Railway Fourth Bureau Group Co., LTD., bid price: 2.9 billion yuan. Key words: engineering construction information, engineering construction, engineering news

Schematic diagram of Anhui section bid Division and winning bidder of Shanghai-Chongdu-rong high-speed Railway

Candidate of construction supervision bid

HNJL-1 bid: Shanghai Advance Construction Supervision Co., LTD., bid price: 38.55 million Yuan; HNJL-2 bid: Tianjin New Asia-Pacific Engineering Construction Supervision Co., LTD., bid price: 40.8 million yuan; HNHFSNJL: Shanghai Tianyou Engineering Consulting Co., LTD. Winning bid: 27,734,700 yuan. Editor/Zhao E


Comment

Related articles

Central enterprises

The 12th Hydropower Bureau and the Zhejiang Emergency Department build a rescue alliance

08-19

Central enterprises

XCMG Group and Rio Tinto Group sign a global cooperation framework agreement

08-15

Central enterprises

China Power Construction and State power Investment leaders to deepen energy cooperation

07-20

Central enterprises

China Construction Third Engineering Bureau Zhejiang Transportation Project

07-18

Central enterprises

5.635 billion yuan! China Energy Construction won the bid for Jinneng Phase III project

07-15

Central enterprises

National Railway Administration and Chongqing City Sign Cooperation Agreement

07-04

Collect
Comment
Share

Retrieve password

Get verification code
Sure