On Oct 13, 2022, the announcement of the successful candidates for the total construction price contract of the Nanjing hub and the Nantong pre-station project of the new Shanghai-Nanjing-Hefei high-speed Railway was released. The project will begin full construction in October.
Project overview
The newly built Shanghai-Nanjing-Hefei high-speed Railway starts from the newly built Shanghai Baoshan Station at Shanghai hub and ends at Hefei South Railway Station at Hefei hub. The operation length of the project is 553.76km, including 519.05km of new line, 471.518km of bridge and 25.099km of tunnel, with a bridge-tunnel ratio of 95.68%.
There are 16 stations on the whole line, of which 10 are newly built, which are Baoshan, Chongming, Qidong, Haimen, Rugao, Huangqiao, Taizhou, Yizheng, Nanjing and Dashu stations. Five stations were rebuilt, namely Taicang, Nantong, East Yangzhou, Chuzhou and Feidong stations; The use of the existing station 1, for Hefei South Station.
This bidding agent construction project is the reconstruction project of Nanjing Hub and Nantong area, and the construction site is located in Nanjing and Nantong City, Jiangsu Province.
Planned construction period: 5 years, planned start date: October 2022, planned completion date: October 2027.
Nanjing hub
Shanghai-chongdu-rong main line DK379+339.28 to DK427+948.09, the length of the line 46.30 kilometers. Nanjing North Railway Station Huyurong Depot, Nanjing North Huyurong high-speed train running line, Nanjing North high-speed train Operation Center and comprehensive maintenance area.
It includes the reconstruction of Beijing-Shanghai passenger car line, the reconstruction of Beijing-Shanghai freight car line, the reconstruction of Ningqi line, the construction of Ningqipu North link line, the reconstruction of Linpu line, the reconstruction of ethylene special line, and the construction of the whole passenger station access section line.
The main stations are the new Pusu station of Nanjing North Railway Station, the forest station station, the reconstruction of Gaoli Station, Yongningzhen Station, Yinzhuang Station and Puzhen Station, the new Nanjing North railway service return section and the whole passenger station project.
Nantong region
Shanghai-chongdu-rong main line DK154+636.710 to DK172+717.27, the length of the line 18.08 kilometers. It includes reconstruction of Chenqiao Railway Line, reconstruction of Nantong Station, reconstruction of Qidong Railway Station, construction of Qidong passenger terminal and maintenance return section, running line of Nantong bullet train and expansion of Nantong bullet train operating station. Key words: engineering news, engineering construction, engineering construction information
Construction proposed winning bidder
The total construction price of the new Shanghai-Nanjing-Hefei high-speed railway in Nanjing hub and Nantong area is divided into four bidding sections, which are as follows:
Bid section Ⅰ (BYJZQ-01SG) : Nantong pre-station project, proposed winning bidder name: China Railway 10th Bureau Group Co., LTD., bid price: 2.72 billion yuan; Section Ⅱ Bid (BYJZQ-02SG) : Shanghai-Chongdu-Nanjing Pre-station Project, Proposed winning bidder name: China Railway Shanghai Engineering Bureau Group Co., LTD., bid price: 3.639 billion yuan; Section Ⅲ (BYJZQ-03SG) : The East station front project of the transformation of the General Speed Field of Nanjing North Junction. The proposed winning bidder: China Railway 24 Bureau Group Co., LTD., bid price: 2.824 billion yuan; Section Ⅳ Bid (BYJZQ-04SG) : The west station front project of Nanjing North Hub General Speed Field renovation. The proposed winning bidder name: China Railway Third Bureau Group Co., LTD., bid price: 2.9 billion Yuan.
The supervisor proposes the winning bidder
Nantong Pre-station Project -01JL bid: Shanghai Advance Construction Supervision Co., LTD., bid price: 21.95 million yuan; Huyun-rong Nanjing Hub Pre-Station Project -02JL bid: Shanghai East China Railway Construction Supervision Co., LTD., bid price: 26,782,300 yuan; Nanjing North Junction Prestation Project on the east side of Universal Speed Yard Reconstruction -03JL bid: China Railway Safety Engineering Consulting Co., LTD., Winning price: 22.510 million yuan; Nanjing North Hub Universal Speed Field Reconstruction West Station Front Project -04JL bid: Shanghai Tianyou Engineering Consulting Co., LTD., Winning price: 3,054,492 million Yuan. Editor/Zhao E