Photovoltaic
Xinjiang Shache 2 million kW integrated optical storage project started
Seetao 2022-10-20 17:38
  • The project will be built in three phases and is expected to be connected to the grid in 2024
  • The project is Guangdong Energy Group's first autonomous region photovoltaic project in Xinjiang
Reading this article requires
6 Minute

Recently, Xinjiang Shache County 2 million kW light storage integration project in the photovoltaic industrial park officially started construction. According to the introduction, the project is located in Shache County photovoltaic industry base, about 30 kilometers east of Shache County, the construction of 500 MW /2000 MW energy storage supporting 2000 MW photovoltaic power generation project, the investment is about 12.8 billion yuan, the land is about 60,000 mu, the annual average power generation is about 4 billion KWH. The project is to be constructed in three phases and is scheduled to be connected to the grid in 2024.

Chen Kuan, deputy general manager of Guangdong Energy Group in Xinjiang, said, "This project is Guangdong Energy Group's first 2 million kilowatt photovoltaic project in Xinjiang, and the first photovoltaic project supported by government financial instruments. In 2022, 500 million yuan is planned to be completed and 500 million yuan will be paid for administration. After the completion of the project, the annual output value will be about 1.05 billion yuan, profits and taxes will be 314 million yuan. About 100 new jobs."

The project is to implement the important instructions of Ma Xingrui, Secretary of the Party Committee of the Autonomous Region, on the "layout of 20 million kW new energy projects in Kashgar", and the Kashgar Administrative Office signed a cooperation agreement with Guangdong Energy Group to invest in the construction of 3.5 million kW photovoltaic power generation and clean coal cogeneration projects in Kashgar. Guangdong energy group, take concrete actions to actively promote the guangdong light energy yarkant 2 million kilowatts integration project, storage configuration sufficient professionals to carry out the project to promote work, focus on the yarkant departments at all levels, power grid companies as well as the design of special docking work, further enhance work efficiency, actively promote the project construction as soon as possible.

Guangdong energy group yarkant 2 million kw TuiJinZu optical storage integration project leader Eunice li said: "the next step, our company will be in the autonomous region party committees and governments at all levels of support, make full use of the development of new energy projects in xinjiang opportunity comes once in a blue moon, good environment, in yarkant scenery fire can complement each other clean energy storage base. Ensure the smooth construction of the 2 million kW light storage integration project in Shach County, ensure safety, quality and progress, and make due contributions to the economic and social development of southern Xinjiang." Editor/He Yuting

Comment

Related articles

Photovoltaic

Longyuan Power 150MW photovoltaic project was filed

10-17

Photovoltaic

Mechanical completion of JTC PV project in Jurong Island, Singapore

10-14

Photovoltaic

5GW! Indonesia's largest integrated photovoltaic manufacturing project starts construction

10-11

Photovoltaic

India will add new PV capacit

10-10

Photovoltaic

Ayouqijing new tamusin 400,000 kilowatt photovoltaic project started

09-30

Photovoltaic

Datang Yunnan Lukudi Photovoltaic Power Generation Project Starts Construction

09-29

Collect
Comment
Share

Retrieve password

Get verification code
Sure