On Oct 20, 2022, the Zhangye Pumped Storage power Station in Gansu Province was approved by the Gansu Provincial Development and Reform Commission. According to the introduction, Gansu Zhangye pumped storage power station is the national pumped storage medium - and long-term development plan (2021-2035) "fourteen five key implementation projects, Gansu province 2022 provincial key projects, Three Gorges Group key development projects.
Gansu Zhangye Pumped Storage Power Station
Gansu Zhangye Pumped Storage Power Station is located in Ganzhou District and Sunan County, with a total installed capacity of 1.4 million kW, a total investment of 9.626 billion yuan, a rated water head of 576m, and the installation of 4 350MW reversible pump turbine electric generating units. The designed annual power generation and annual pumping consumption are 1.637 billion kWh and 2.183 billion kWh, respectively.
Power station, after the production of the main gansu power grid peak shaving and valley filling, storage, frequency modulation, phase modulation, and emergency backup task, as gansu hexi area clean energy base out a safe and stable operation and reliable, to promote the construction and development of new energy and given, promote local economic and social development has a positive effect.
Since 2021, the country has accelerated the construction of pumped storage, and Gansu Province, which is rich in new energy resources, has ushered in a major opportunity period for the development of pumped storage. Yangtze River Electric Power resolutely implemented the relevant deployment of the Three Gorges Group, strengthened strategic cooperation with Gansu Province, set up a pumped-storage working team, and completed the approval work of Zhangye pumped-storage power Station in Gansu Province with high quality and efficiency.
It is the first pumped-storage power station approved by Yangtze Power and an important achievement of Yangtze Power's "high-level consolidation of large hydropower and high-quality expansion of new space". In the next step, Yangtze Power will strengthen project construction management, work hard and energetically, actively and steadily promote the construction of power stations, and make greater contributions to helping the country build a new type of power system and achieve the "double carbon" goal. Editor/He Yuting