Argentina lithium salt Lake steel structure plant project started
Seetao 2022-10-26 08:51
  • The construction period of the project is 398 days
  • The construction of the project will effectively promote local employment in Argentina, and further optimize the construction of energy and infrastructure
Reading this article requires
3 Minute

On the morning of October 20, 2022, Argentina time, the installation project of steel structure plant and mechanical and electrical equipment in Argentina Centenario-Ratones lithium salt Lake, which was built by Power China, officially started. The owners of Castle Peak Industries and Achman South America Company representatives attended the groundbreaking ceremony.

The project is located in the salt lake of Centenario-Ratones in the Andes Mountains in Salta Province, northwest Argentina, which is known as the "South American Lithium triangle". The altitude is about 4,100 meters. The project duration is 398 days. Water treatment plant structure, equipment and pipeline installation, as well as plant pipe network structure installation.

Centenario-Ratones Salt Lake lithium mine project is characterized by high altitude, frequent mountain winds and large temperature difference between day and night, which is a huge test for lifting and working at high altitude. Power China will give full play to its professional advantages and localization experience, do a good job in project planning and risk identification, and go all out to ensure the project performance. When completed, the project will help build a lithium carbonate plant with an annual capacity of 24,000 tons, adding to Argentina's solar lithium battery industry. Editor/He Yuting

Comment

Related articles

Construction Frontline

China Road and Bridge Corporation signs contract for Uzbekistan road project

10-11

Construction Frontline

Antai New Energy signs contract with Indian EPC company for project

10-10

Construction Frontline

Papua New Guinea National Petroleum Building Pile Foundation Testing Project

10-09

Construction Frontline

Zhongjiang International signs contract for Vanuatu housing construction project

10-09

Construction Frontline

The first new energy project invested and constructed by China Datang in Central Asia

10-05

Construction Frontline

Dongfang Electric signs contract for Ethiopia hydropower project

09-30

Collect
Comment
Share

Retrieve password

Get verification code
Sure