Recently, Fujian Quanzhou Urban Construction State owned Assets Investment Co., Ltd. issued a bidding announcement for the Quanzhou Jinyu Bridge Project. The project is located in Quanzhou, Fujian Province, with a total investment of about 3.7 billion yuan. The bridge construction is about to start.
Project scale
In this project, it is proposed to build 1 super large bridge and 2 interchanges. The total length of the line is 4.481 km. The main bridge of Wuyu Interchange is 533 meters long, the west approach bridge is 1000 meters long, the main bridge is 320 meters long, the east approach bridge is 550 meters long, and the main bridge of Luoxiu Interchange is 1340.994 meters long. The end station is K4+480.994. The road extends eastward along Chengdong Street and connects with the west approach bridge of Jinyu Bridge. The main bridge spans the Luoyang River. The east approach bridge connects Haijiang Avenue and ends at Luosha Avenue.
technical standard
The road width of the main bridge is 45.5m, and it is constructed as a two-way eight lane road. The main approach bridge of the Wuyu Interchange on the west bank has a two-way six lane road; Two way eight lane approach bridge of the main line in Luoxiu Interchange on the east bank; Ramps in the interchange area shall be set as single lane and double lane as required.
Section division
The project construction is divided into two sections, and one section group according to the nature of the project; There are 2 lots and 1 lot group in this bidding.
Section A1: West Bank Main Bridge, West Bank Approach Bridge, Wuyu Interchange, Main Line Bridge of Wuyu Interchange, West Bank Widening Bridge, 2 West Bank Overbridges, West Bank Road Works, West Bank Municipal Pipeline Works and Ancillary Works. The total length is 2.429km.
Section A2: East Bank Main Bridge, East Bank Approach Bridge, Luoxiu Interchange, Luoxiu Interchange Main Line Bridge, 2 East Bank Overpasses, 1 East Bank Medium Bridge, East Bank Road Works, East Bank Municipal Pipeline Works and Ancillary Works. The total length is 2.051994km. Keywords: engineering news, engineering construction information, engineering construction
Planned construction period: the planned construction period of this project is 1080 calendar days, the defect liability period is 24 months, and the planned commencement date is December 14, 2022. Editor/Zhao E