On December 4, 2022, GEPIC Jiuhui Company Yumen Mahuangtan 200 MW Wind Power Project was successfully connected to the grid for power generation.
GEPIC Yuhen Mahuangtan No.1 Wind Farm is located in the Gobi Beach, about 32km northeast of Yumen City, Jiuquan City. The wind energy resource conditions are good. The total investment of the project is about 1.2 billion yuan, and the total installed capacity is 200 megawatts. This project belongs to the second batch of 5 million kilowatts wind power project of Jiuquan Wind Power Base Phase II, and is also the supporting power supply project of Jiuhu ± 800 DC project. The project adopts 50 sets of Mingyang intelligent semi direct drive wind turbine generator units with a single unit capacity of 4.0 MW, a tower height of 100 meters, and a impeller diameter of 173 meters. The annual grid power is about 600 million kWh. The construction of Mahuangtan Wind Power Project has been strongly supported by Jiuquan City and Yumen City, and has been dedicated by all parties. After the completion of the project, about 206000 tons of standard coal can be saved, about 619600 tons of carbon dioxide emissions can be reduced, about 54.18 tons of carbon monoxide emissions can be reduced, about 2381.33 tons of nitrogen dioxide emissions can be discharged, and about 2787.14 tons of harmful substances such as smoke and dust can be discharged, which will reduce air pollution and environmental protection pressure to a certain extent, To promote regional low-carbon development, it will effectively supplement the energy supply of Hexi region, help regional economic development, make positive contributions to local taxes, and achieve coordinated development of economy and environment.
Since the commencement of the project, Jiuhui Company has resolutely implemented the strategic plan for the clean energy industry of the Group Company, strengthened organizational leadership, clarified working ideas, and actively overcome many unfavorable factors such as complex terrain, harsh climate and environment, wind speed exceeding the limit, COVID-19, shortage of construction personnel, etc. On the basis of ensuring safety, it has coordinated all forces and favorable factors to fully pool the wisdom and strength of employees, Promote the project construction with quality and quantity guaranteed, make arduous efforts to achieve the goal of grid connected power generation of the project, and harvest fruitful results.
Prepare well for the rainy day and pave a smooth way in the torrent. After the country put forward the strategic goal of "double carbon", Jiuhui Company firmly seized the historical opportunity of Gansu Province to "vigorously promote the new energy industry in the province to become bigger and stronger", assigned special personnel to follow up and monitor the work, strived for the target of Yumen Mahuangtan 200 MW wind power project, and implemented the leadership system of "one project, one responsible leader, one work plan" according to the working mechanism of "one project, one responsible leader, one working plan", comprehensively organized, guided Coordinate and promote the project preliminary procedures, bidding procurement, construction management, fund raising, completion acceptance, etc. Before the commencement of the project, the company will organize the management personnel of all participating units to review all drawings, construction plans, emergency plans and special construction plans of the project repeatedly, plan the wage payment requirements for migrant workers and the management methods for rewards and punishments for safe and civilized construction on site in advance, so as to take precautions. Coordinate the design institute to optimize the design and compare the cost accounting. For the installation and acceptance of fan anchor bolts, foundation reinforcement binding, foundation concrete pouring, secondary grouting, fan hoisting and other important links, technical disclosure and safety disclosure were organized for many times before the commencement. The Yumen Project Department was set up to transfer key technical personnel from all disciplines of the project to work at the project site to fully promote project progress, equipment arrival, formalities handling, peripheral coordination, etc. Strengthen the equipment expediting, implement the equipment arrival list system, achieve the goal of "marking goods - arrival - cancellation", arrange special personnel to the factory for expediting, timely follow up the logistics information, implement relay or special vehicle transportation for equipment and materials that affect the construction progress, minimize the vehicle detention time, and win valuable time to ensure the timely arrival of materials.
The more difficult it is, the more courageous it is. In strict accordance with the arrangement and deployment of the Group Company, the Company plans the project quality, safety and progress as a whole. With the goal of "high standard commencement, high level construction and high quality production", the Company reasonably allocates construction resources and adjusts operation time. The Project Department and all participating units actively give up vacations and continue to fight, braves the severe cold, extreme heat, epidemic prevention, and focuses on construction, so as to fully promote the project construction. The daytime temperature at the construction site in July reached more than 40 degrees Celsius, which is not conducive to the pouring of mass concrete. The project site adjusted the operation time in a timely manner. The pouring work was carried out from 6 p.m. to 9 a.m. the next day. The management personnel ate and stayed at the site and watched the progress all night to ensure the smooth progress of the construction. In August, the hoisting of fans entered the peak period. The construction site selected strong wind weather to install and debug fans, and intensified hoisting in light wind weather. Scientific use of time was made to seize the construction period. During the whole hoisting process, the relevant responsible persons and safety management personnel of the company and all participating units will stand by and supervise the whole process, organize daily shift meetings, carry out safety, technical disclosure and on-site safety problem feedback, and build a safe defense line for the project construction.
Set your goals and work hard to achieve great results. During the project construction, the team members and middle managers of the company stick to the front line of construction, take the lead, command from the front, strengthen management, regularly organize project promotion meetings, help, guide and solve problems in the process of project promotion, and work with project personnel to promote full capacity grid connected power generation of the project. All staff of the Yumen Project Department of the Company work overtime and work on wall charts. They insist on holding project progress coordination meetings every night to coordinate and solve the difficulties encountered that day, define the responsibilities of each participating unit, and assign the tasks to each person to ensure efficient work the next day; As there are many problems that need to be solved through coordination and involve a wide range of areas, the employees of the Project Department go out early and come back late every day, each person carries a charging bank with him/her, and the power supply is supplemented at any time to ensure smooth communication; When the vehicles are busy, they walk back and forth to each working face of the project site, ensuring the smooth implementation of the project construction.
Make concerted efforts to overcome difficulties and show responsibility in the fight against the epidemic. During the project construction, the epidemic situation in Gansu was repeated. Especially since the outbreak of the new round of COVID-19, the company has adhered to the "two hands and two errors" of epidemic prevention and control and project construction in accordance with the relevant requirements of the group company on overall planning of epidemic prevention and control and energy supply assurance. In terms of epidemic prevention and control, the company has focused on "external prevention input", further strengthened on-site prevention and control measures, strengthened management of construction sites and personnel, and provided various protective equipment for construction personnel in a timely manner, Fully carry out the disinfection and disinfection and sterilization work, actively coordinate and solve the difficulties of project personnel in their work and life, fully implement the logistics support work such as clothing, food, housing and transportation of project site personnel, and maximize the safety of the site; In terms of project construction, we actively enlisted the support of the provincial electric power company, and handled a series of formalities before grid connection, such as equipment commissioning, grid connection technical data review, and grid connection prerequisites confirmation, through online methods, to ensure the successful grid connection of the company's Yumen Mahuangtan 200 MW wind power project.
Party building leads the development of precision and performance in service. During the construction of the project, the company attaches great importance to playing the leading and guaranteeing role of party building, actively promotes the integration and mutual promotion of party building and project construction, and ensures the high-quality construction of the project by focusing on the leading role of party building. We will continue to deepen the construction of "posts, districts and teams", promote the integration and mutual promotion of party building and project construction, place the education of party members on the project construction site, encourage party members, cadres and technical backbones to take the lead in taking root in the Gobi Desert, shoulder the burden, take the responsibility, temper growth, overcome difficulties, fully play the vanguard role of party members, and let the party flag fly high in the front line of project construction; The Youth League Committee of the Company set up a youth commando for the new energy "double excellence" project, gave full play to the role of young workers as a fresh force and commando in the project construction, guided and encouraged the youth of the League members to march ahead and fight bravely. With rock solid confidence, seize the moment, and perseverance, the Youth League Committee enthusiastically participated in the construction of the Company's projects, set off a boom of big and special efforts, and played an important role in ensuring the smooth implementation of the project.
At present, the "Rush" of new energy development and construction has been heard in all project sites of Jiuhui Company. The company will earnestly implement the strategic deployment of "accelerating the green transformation of the development mode, deeply promoting the prevention and control of environmental pollution, actively and steadily promoting carbon peak and carbon neutralization" proposed in the report of the 20th National Congress of the Communist Party of China, continue to uphold the original intention of strengthening, expanding and optimizing the new energy industry, keep in mind the responsibility and mission of green development With firm determination and solid work, we will stride forward to a new future, write a new chapter of chasing the trend and make new and greater contributions to the high-quality development of the new energy industry of the Group. Editor/Xu Shengpeng