Construction of Quzhou Songyang Section of Zhejiang Quzhou Lijiang Railway
Seetao 2022-12-29 10:05
  • The main line of the second phase of Quzhou Lijiang Railway is 94.8 km long, with a design speed of 200 km/h
  • The project is planned to be completed and opened to traffic in 2026, and the approved budget is 17.633 billion yuan
Reading this article requires
22 Minute

On December 28, 2022, the Quzhou Songyang Section of Quzhou Lijiang Railway, which was invested and constructed by Zhejiang Communications Group, was officially started in Suichang County, Lishui City. Li Feng, Director of the Standing Committee of Lishui Municipal People's Congress, Yu Ji, Deputy General Manager of Zhejiang Communications Group, Wu Songping, Vice Mayor of Quzhou, Zhu Lei, Vice Mayor of Lishui, and others attended the event.

As an important project supporting the construction of Quli "Grand Garden", the second phase of the main line of Quli Railway is 94.8 km long, with a design speed of 200 km/h, and an approved budget estimate of 17.633 billion yuan. It is planned to be completed and opened to traffic in 2026. This is a key project for Zhejiang Communications Group to set off a new round of major transport projects and accelerate the construction of the transport rail network in the process of accelerating the construction of a high-level transport province.

After the Quzhou Lishui Railway is completed and opened to traffic, it will only take about 55 minutes to travel from Quzhou to Lishui by train. There is no need to bypass Jinhua. The original one and a half hour drive will be shortened by about 40%. The convenient transportation channels between central and southwest China and Lishui and Wenzhou through Quzhou will also be completely opened.

A golden belt connecting five mountainous counties in southwest Zhejiang

Quzhou Lijiang Railway, located in the southwest of Zhejiang Province, is a national medium and long-term railway network planning and multi-level rail transit planning project in the Yangtze River Delta, and an important project to comprehensively implement the construction of Zhejiang Grand Garden and support the development of the ecological tourism belt in the southwest of Zhejiang Province. The whole line of the project connects five mountain counties in total, namely Qujiang District, Longyou County, Suichang County, Songyang County, and Liandu District. It is of great significance to improve the layout of the road network in the southwest of Zhejiang, realize the integration of Songyang and Suichang into the "one hour Hangzhou Metropolitan Circle", support the revitalization of the old revolutionary base areas, and promote the high-quality development of the mountain counties along the line.

Quzhou Lishui Railway starts from Quzhou City in the west and ends at Lishui City in the east, with a total length of 160.1 km. It is constructed according to the standard of new double line, passenger and freight lines, and design speed of 200 km/h, with a total investment of 26.72 billion yuan. The west end connects Shanghai Kunming Railway, Jiujing Quzhou Railway and Hangzhou Quzhou Railway via Quzhou area, and the east end connects Lishui area and connects Jinliwen Railway. The project construction shall be implemented by sections.

Among them, the first phase of the project is Songyang Lishui Section, which starts from Songyang Station of Quning Railway, passes through Songyang County and Liandu District of Lishui City, and ends at Lishui Station of Jinliwen Railway, with Songyang Station, Dongxiyan Station and Lishui Station. The main line is 65.3 km long, and the construction will start in December 2020. As of December 25, the completed investment was 2.8212 billion yuan, accounting for 31.05% of the total investment.

The second phase of the project is Quzhou Songyang Section, which starts from Qujiang Station of Hangzhou Quzhou Railway, passes through Qujiang District and Longyou County under the jurisdiction of Quzhou City, Suichang County and Songyang County under the jurisdiction of Lishui City, and ends at Songyang Station of Quning Railway, with four stations, namely Qujiang, Longyou, Suichang West and Songyang.

With the construction of Quzhou Lijiang Railway, together with Jinliwen Railway, Hangzhou Quzhou Railway and Hangzhou Huanghua Railway, the region will form a "big garden" railway ring in Zhejiang Province, and become the "golden belt" of the big garden in the rear of the Yangtze River Delta, greatly improving regional traffic conditions, driving the development of tourism economy, and promoting high-quality development of the regions along the line and regional economy.

After the opening of the line, the ethnic township tourism in Qujiang, the bamboo industry in Suichang, the tea industry in Songyang, and the booming green energy and digital economy along the line are expected to achieve greater development through closer personnel exchanges and benefit the people along the line. "We will expand the space for development in an all-round way with major transportation projects. The commencement of the second phase of the Quli Railway will bring Suichang into the 'one hour traffic circle' of Zhejiang Province eastward," said Chen Peng, deputy director of Suichang County Development and Reform Bureau and a temporary cadre of Zhejiang Communications Group in mountainous counties.

In the southwest of Zhejiang, the mountains are vast and undulating, and the river network is dotted with stars. "When I took out my mobile phone, I saw the beautiful scenery of blue sky, white clouds, green water and green mountains. Many city people yearned for the landscape here." Mr. Zhang, the boss of farmhouse music in Shilantou Village, Suichang County, sighed: "The construction of the railway will certainly attract more people to come here, and our life will be more and more prosperous." As the project was about to start, Mr. Zhang couldn't help smiling with understanding, A "road out of the mountain" that allows mountain people to bid farewell to the hard days of trekking through mountains and rivers, and a "road to prosperity" that enables the development of ecological economy in mountain areas are further becoming reality.

Pilot project of whole process consultation

"Due to the large topographic relief and complex geological conditions along the Quzhou Lijiang Railway Phase II Project, the bridge tunnel ratio is as high as 89.9%, which also brings great challenges to our construction. With the help of the" whole process consultation "model, which is the first in the national railway field, we conducted sufficient geological exploration and construction scheme research, and professionally and efficiently promoted the feasibility study, land use approval and other preliminary work, laying the foundation for smooth commencement." Xie Zijing, Deputy Commander of Quli Railway Construction Headquarters of Zhejiang Communications Group, introduced.

It is understood that the second phase project of Quzhou Lijiang Railway is the first railway project in China to adopt full process engineering consultation. Through the strong cooperation of "construction unit+consulting unit" and the establishment of a road local coordination mechanism, the second phase of Quzhou Lijiang Railway Project has repeatedly refreshed its pace of advancement with the support of national policy oriented development financial instruments and local governments.

Dai Wenwei, the Quli Railway Construction Headquarters of Zhejiang Communications Group, introduced: "In the face of many problems in the early work, such as many special topics, tight time, heavy tasks and repeated epidemics, we have cooperated with many parties to establish a working mechanism of special shifts and special personnel to monitor and control the difficult points. After the approval of the project feasibility study, we quickly obtained the preliminary design approval, followed by the early implementation of the project bidding. At the same time, we worked with 2 cities and 4 counties (districts) 27 units of the Ministry of Natural Resources of the People's Republic of China worked closely to complete the review and confirmation of 43 documents submitted for approval for land use in advance, and obtained the reply from the Ministry of Natural Resources in a short time. "

Create a new highland for railway intelligent manufacturing

For project construction, land acquisition and demolition shall be carried out first. It is understood that the second phase of Quzhou Lijiang Railway will start the land acquisition and demolition work in 2023, and it is planned to popularize the "digital land acquisition and relocation" platform that is mature in the current phase I project in June. Through this platform, the expropriated can not only check and understand the information about the land acquisition and relocation policy and compensation progress at any time, but also use a series of technical means, such as UAV 3D photography, building electronic sand table for land acquisition and relocation, and the command cabin for land acquisition and relocation, to accurately monitor and intelligently supervise the land acquisition and relocation work that involves large amounts of money, has complex relationships, and is closely related to the interests of the masses.

In addition, the "black technologies" such as 3D section scanner and three arm drilling jumbo used in the first phase of Quzhou Lijiang Railway also add "digital" wings to the construction of the second phase of the project. Keywords: engineering news, engineering construction, engineering construction information

Wang Jinbao from the Quli Railway Construction Headquarters of Zhejiang Communications Group displayed the "key technology" in the project construction, One side introduced: "During the construction of the Quzhou Lijiang Railway Project, we actively innovated the tooling process, effectively reducing the number of operators in high-risk construction environments, and also providing strong equipment support for intelligent construction throughout the life cycle of the project. Taking the three arm rock drilling jumbo as an example, workers can operate the tunnel construction while sitting in the equipment, reducing the harm of noise and dust to the human body. The number of workers in tunnel face construction has also decreased from the original 20 To 10, mechanized excavation ensures that the average daily footage of the tunnel is 7 to 8 meters, which is 50% more efficient than manual construction. " Editor/Zhao E


Comment

Related articles

Transportation

Road Construction holds 2024 New Quality Development Technology Seminar

11-26

Transportation

Shanghai Zhoudeng Expressway officially starts construction

10-15

Transportation

The terminal building of Dalian New Airport has started construction!

10-14

Transportation

70 billion yuan intercity railway project is coming!

10-14

Transportation

Seymour is about to build a road

10-12

Transportation

The Kazakhstan Mongolia highway connection is about to be launched

10-12

Collect
Comment
Share

Retrieve password

Get verification code
Sure