Shandong Rizhao transportation construction plan investment 117.1 billion yuan
Seetao 2023-01-27 10:41
  • Issuance of the 2023 urban planning and construction management plan of Rizhao City, Shandong Province
  • Among them, 9 railway construction projects, 11 highway construction projects, 18 port construction projects, and 1 airport project
Reading this article requires
35 Minute

The total investment of the transportation construction plan project in Rizhao City, Shandong Province in 2023 is 117.119 billion yuan, and the annual investment is planned to be 20.161 billion yuan, focusing on the construction of 39 transportation infrastructure projects.

Railway construction plan

There are 9 railway projects, including 2 continuing projects, 4 new projects and 3 early projects. The total investment is 26.134 billion yuan, with 5.811 billion yuan planned to be completed in 2023.

1. The reconstruction project of passenger transport facilities in Rizhao Station will be continued. The investment is 1.921 billion yuan. The construction period is from 2021 to December 2024, and the planned investment in 2023 is 800 million yuan.

2. The expansion and reconstruction project of Ping-Lan Railway will be continued. The total length is about 32.97 kilometers, and the investment is 2.051 billion yuan. The construction period is from 2021 to December 2023, and the planned investment in 2023 is 951 million yuan.

3. Weifang-Suqian Railway, the auxiliary channel of Beijing-Shanghai High-speed Railway, was newly started. About 49.8 kilometers in Rizhao, there are Wulian North Station and Juxian North Station, with an investment of about 9.442 billion yuan. The construction period is from November 2023 to June 2028, and the planned investment in 2023 is 2.6 billion yuan.

4. The auxiliary channel railway project of the Qingdao-Beijing-Shanghai high-speed railway was newly started. Rizhao is about 15.34 kilometers long, with an investment of about 2.56 billion yuan. The construction period is from November 2023 to June 2028, and the planned investment in 2023 is 1.06 billion yuan.

5. The railway project in the south operation area of Lanshan Port Area of Rizhao Port has started. The track laying mileage is about 20.8 kilometers and supporting facilities, with an investment of 860 million yuan. The construction period is from July 2023 to July 2025, and the planned investment in 2023 is 150 million yuan.

6. The second phase of the railway project in the south of Shijiu Port Area of Rizhao Port was newly started. The track laying mileage is about 20 kilometers and supporting facilities, with an investment of 250 million yuan. The construction period is from November 2023 to December 2024, and the planned investment in 2023 is 150 million yuan.

7. Early stage of Wulian North Station supporting facilities project of Beijing-Shanghai high-speed railway auxiliary channel. Build a public transport passenger transfer center, including tourist distribution center, special agricultural products and tourism products exhibition hall and other facilities; Supporting construction of bus and social vehicle parking spaces, gas stations, etc. Supporting construction of Zhanqian Avenue, Sichuan Road, Yingbin Road, etc. The investment is about 600 million yuan, and the preliminary planning demonstration will be carried out in 2023, with a total investment of 50 million yuan.

8. Early stage of the construction project of the integrated passenger transfer hub at Juxian North Station, the auxiliary channel of Beijing-Shanghai high-speed railway, and other supporting infrastructure projects. Build supporting infrastructure such as high-speed railway passenger transport service center, passenger distribution and transfer center, maintenance and security inspection center, supporting rooms, and relevant auxiliary facilities such as 2000 parking spaces and 600 supporting charging piles. The investment is about 750 million yuan, and the preliminary planning demonstration will be carried out in 2023, with a total investment of 50 million yuan.

9. Early stage of Rizhao - Beijing-Shanghai high-speed railway auxiliary channel railway project. The planned line is led from the North Songyuan line and connects Wulian North Station, with a total length of about 55 kilometers and an investment of about 7.7 billion yuan. The preliminary planning demonstration will be carried out in 2023.

Highway construction plan

There are 11 projects in total, including 2 continuing projects, 8 new projects and 1 early project. The total investment is 34.156 billion yuan, with 8.92 billion yuan planned to be completed in 2023.

1. Continued construction of Lanshan Port Shugang Expressway Project. The total length is about 12 kilometers, two-way four-lane, and the investment is 2.466 billion yuan. The construction period is from 2021 to December 2024, and the planned investment in 2023 is 1.5 billion yuan.

2. The expansion project of Liangcheng-Fenshui section of G15 Shenyang-Haihai Expressway was newly started. It has a total length of about 61 kilometers, two-way eight lanes, and an investment of 8.35 billion yuan. The construction period is from June 2023 to June 2026, and the planned investment in 2023 is 3 billion yuan.

3. The Rizhao Section of Dongliang Expressway was newly started. The total length is about 73 kilometers, two-way four-lane, and the investment is 10.6 billion yuan. The construction period is from October 2023 to October 2026, and it is planned to complete the investment of 1 billion yuan in 2023.

4. The construction of Linri Expressway was newly started. The total length is about 20 kilometers, two-way six-lane, and the investment is 4.2 billion yuan. The construction period is from December 2023 to December 2026, and the planned investment in 2023 is 500 million yuan.

5. The west extension project of Shugang Road in Rizhao Port of the 220 Pingri Provincial Highway was newly started. The total length is 57 kilometers and the investment is 3.45 billion yuan. The construction period is from August 2023 to December 2025, and the planned investment in 2023 is 1.5 billion yuan.

6. The reconstruction and expansion project of Rizhao Section of the National Highway 518 was newly started. The total length is 24 kilometers and the investment is 1.65 billion yuan. The construction period is from December 2023 to December 2026, and the planned investment in 2023 is 250 million yuan.

7. The large and medium maintenance project of national and provincial roads has been started. The route maintenance mileage is 50 kilometers, and the investment is 100 million yuan, which will be completed in 2023.

8. In the early stage of reconstruction project of Wulian urban area of National Highway 342 Rifeng Line. With a total length of about 32 kilometers, it is a Class I highway with an investment of 1.94 billion yuan. The preliminary planning demonstration will be carried out in 2023.

9. The first phase of the optimization and upgrading project of the collection and distribution system in Shijiu Port Area was newly started. It consists of 2 sub-projects: 1 interchange is set up between Linyi South Road and Shugang Expressway; An interchange will be set up between Linyi South Road and Shenzhen Road with an investment of 240 million yuan, which will be completed in 2023.

10. The viaduct project of Rigang Section of the South Coast Highway will be continued. It starts at the right turn ramp access of Longwang River Interchange on Shugang Avenue and ends at the intersection of Anlan Avenue and Nanyanhai Road, with a total length of 3.48 kilometers and two-way ten-lane. One viaduct with two-way six-lane is set along the whole line; The two-way four-lane auxiliary road on the ground has a total investment of 660 million yuan. The construction period is from 2022 to December 2023, and the planned investment in 2023 is 330 million yuan.

11. Other rural highway construction and maintenance projects have started. The road network has been upgraded by 126 kilometers, 17 dangerous bridges have been reconstructed, and 185 kilometers of security projects have been implemented. It is planned to complete the investment of 500 million yuan in 2023.

Port construction plan

18 projects, including 14 continuing projects, 3 new projects and 1 early project. The total investment is 56.679 billion yuan, and 5.43 billion yuan is planned to be completed in 2023.

1. The supporting ore terminal project of Rizhao Iron and Steel Base will be continued. A 400000-ton iron ore berth and supporting project will be built with an investment of 2.82 billion yuan. The construction period is from 2016 to December 2024, and the planned investment in 2023 is 300 million yuan.

2. Continued construction of the supporting finished product wharf project of Rizhao Iron and Steel Base. Two 40000 tonnage and two 10000 tonnage general cargo berths and supporting projects will be constructed with an investment of 2.21 billion yuan. The construction period is from 2018 to December 2023, and the planned investment in 2023 is 100 million yuan.

3. Continued construction of the South Harbor Channel Project in the north operation area of Lanshan Port Area, Rizhao Port. The one-way channel for 300000 tonnage bulk cargo ships will be constructed, with a length of 13.95 kilometers and an investment of 1.783 billion yuan. The construction period is 2019 to December 2024, and the planned investment in 2023 is 100 million yuan.

4. The construction of the general berth project of the north second jetty in the north operation area of Lanshan Port Area of Rizhao Port will be continued. One 40000 tonnage and three 100000 tonnage general berths will be built with an investment of 1.63 billion yuan. The construction period is 2020 to December 2024, and the planned investment in 2023 is 300 million yuan.

5. The construction of # 18, # 20 and # 22 general berths in the south operation area of Lanshan Port Area of Rizhao Port will be continued. Two 100000 ton general berths, one 200000 ton general berth and corresponding supporting equipment will be constructed with an investment of 1.15 billion yuan. The construction period is from 2022 to December 2024, and the planned investment in 2023 is 200 million yuan.

6. Continued construction of Lannan # 17 berth project in Lanshan Port Area of Rizhao Port. The construction of a 200000 ton general bulk cargo berth (and related supporting facilities, with an investment of 470 million yuan. The construction period is from 2022 to December 2023, and the investment of 45 million yuan is planned to be completed in 2023.

7. The reconstruction and expansion project of bulk grain storage and transportation system in the south operation area of Lanshan Port Area of Rizhao Port will be continued. The construction of a 1200 ton/hour ship unloading double line, 18 cement silos with a single warehouse of 10000 tons, 2 car loading towers, 1 loading building, and the unloading capacity of 9 # berth reach 6.9 million tons/year, with an investment of 796 million yuan. The construction period is from 2022 to December 2023, and the planned investment in 2023 is 45 million yuan.

8. Continued construction of the automatic transformation project of the loading and unloading process system in the rear yard of Lannan # 11 berth in Lanshan Port Area of Rizhao Port. Seven ore storage yards and their supporting dedusting pump houses, pools, substations, loading buildings and other supporting facilities will be constructed, with an annual turnover of 15 million tons and an investment of 1.7 billion yuan. The construction period is 2020 to December 2024, and the planned investment in 2023 is 200 million yuan.

9. The construction project of the south storage yard of the south jetty in the south operation area of Lanshan Port Area of Rizhao Port will be continued. The construction of 740000 square meters of storage yard, road hardening, complex building, substation and other supporting auxiliary facilities, with an investment of 550 million yuan. The construction period is from 2022 to December 2023, and the planned investment in 2023 is 150 million yuan.

10. Continued construction of the process engineering in the east of Shijiu Port Area, Rizhao Port. Relying on berths # 7 and # 9 in the east of Shijiu Port Area, two wharf belt conveyors and supporting equipment and facilities are arranged to realize two specialized storage yards and two simple storage yard lines, with an investment of 480 million yuan. The construction period is from 2022 to December 2023, and the planned investment in 2023 is 300 million yuan.

11. The Rizhao Port Grain Base Project will be continued. One 100000 ton bulk grain special berth will be rebuilt, 41 12000 ton grain silos will be built, with a total storage capacity of 492000 tons, and corresponding facilities will be built, with an investment of 1.44 billion yuan. The construction period is from 2022 to December 2024, and the planned investment in 2023 is 500 million yuan.

12. Continued construction of the expansion project of the storage yard of berth # 14 # 15 in the south area of Shijiu Port Area, Rizhao Port. The 12 portal cranes of the wharf were replaced by 6 grab ship unloaders, and 6 specialized ore yards were expanded in the west of the existing specialized yard, with an investment of 1.56 billion yuan. The construction period is from 2022 to December 2025, and the planned investment in 2023 is 250 million yuan.

13. Continued construction of the container terminal reconstruction project in Shijiu Port Area of Rizhao Port. Rebuild the # 9 - # 14 bulk cargo berths in the West Zone as special berths for containers, and construct remote control quay bridges, rail cranes, automatic storage yards, remote control buildings, etc. with an investment of 2.65 billion yuan. The construction period is 2020 to December 2023, and the planned investment in 2023 is 400 million yuan.

14. The second phase of the project of moving coal from the east to the south in Shijiu Port Area of Rizhao Port will be continued. The South 8 # berth will be transformed into a specialized coal launching berth, and a car dumper room and related supporting facilities will be built. Two new car dumpers and two ship loaders will be purchased, with a designed annual throughput of 25 million tons. The investment is 1.45 billion yuan. The construction period is from 2022 to December 2024, and the planned investment in 2023 is 140 million yuan.

15. The LNG Terminal Project in Lanshan Port Area of Rizhao Port is newly commenced. Including the terminal, channel and breakwater, the construction scale is 3 million tons/year of LNG ashore, and the investment is 6.49 billion yuan. The construction period is from June 2023 to December 2026, and the planned investment in 2023 is 600 million yuan.

16. The transformation and upgrading project of Rizhao Port has started. In the first stage of the project, 7 berths and supporting storage yards of 100000 to 300000 tons of coal, ore and general purpose will be built in berths # 9 - # 13, # 16 and # 17. In the second phase, the functions of the east and northeast operation areas of Shijiu Port will be transformed into passenger transport and containers, with an investment of 27.8 billion yuan. The construction period is from June 2023 to December 2029, and it is planned to complete the investment of 1 billion yuan in 2023.

17. Rizhao Port production facilities upgrading and supporting projects have started. 1 billion yuan will be invested in upgrading and upgrading the production supporting facilities such as the storage yard, roads and workshops in the port area. The construction period is from January 2023 to December 2024, and the planned investment in 2023 is 800 million yuan.

18. The early stage of the export pipeline project of the LNG terminal in Lanshan Port Area of Rizhao Port. The newly-built export pipeline is about 39 kilometers long, passing through Donggang District and Lanshan District, and connecting with the Qinghai-Nanjing pipeline, with an investment of 700 million yuan. The preliminary planning demonstration will be carried out in 2023.

Airport construction plan

1. The preliminary stage of the project of Shandong Provincial Navigation Industry Demonstration Center. The project is located in the west of Rizhao Airport, covering an area of 45 mu. It is planned to build 13000 square meters of comprehensive support building, 5000 square meters of navigable aircraft hangar, 1600 square meters of unmanned aircraft hangar, 11000 square meters of apron and related supporting facilities. With a total investment of 150 million yuan, the preliminary planning demonstration will be carried out in 2023.Editor/Ma Xue

Comment

Related articles

Transportation

Shanghai Zhoudeng Expressway officially starts construction

10-15

Transportation

The terminal building of Dalian New Airport has started construction!

10-14

Transportation

70 billion yuan intercity railway project is coming!

10-14

Transportation

Seymour is about to build a road

10-12

Transportation

The Kazakhstan Mongolia highway connection is about to be launched

10-12

Transportation

Jiangsu Changzhou Metro Line 6 starts construction

10-07

Collect
Comment
Share

Retrieve password

Get verification code
Sure