As the first stop of Tongwei's large-scale visit to various industrial bases in 2023, recently, a special communication team walked into the construction site of the 25GW photovoltaic module project of Tongwei Solar Yancheng Co., Ltd., engineering vehicles loaded with pipe pile materials entered the site one by one, and pile drivers roared , making the strongest sound on the surface, the workers are busy and focused, and a scene of construction in full swing jumps out.
The Yancheng project has a planned production capacity of 25GW, covers an area of more than 950 mu, has a total construction area of 600,000 square meters, and has a total of 27 individual buildings. In order to ensure the progress of the project, more than 60 pile drivers were operating at the same time at the site, and 80% of the pile foundation construction had been completed. During the peak construction period, 3,000 workers will work on site at the same time, and it is expected to be put into operation in the first half of this year. Li Songqiang, Director of Engineering Department of Tongwei Solar Yancheng Co., Ltd. introduced.
Li Songqiang, Director of Engineering Department of Tongwei Solar Yancheng Co., Ltd. introduced the project construction
Yancheng, where the project is located, is located in the eastern coastal area of China. The groundwater level is high, and the soil is mostly liquefied soil. A large number of pile foundations must be constructed to ensure safe production in the factory area. At the same time, due to differences in geological conditions, previous project construction experience cannot be replicated. The Yancheng module project is currently the most difficult project among Tongwei solar projects.
Faced with challenges such as tight construction schedules, heavy tasks, high standards, and difficult construction, Tongwei Components Yancheng Project Department organized construction parties and supervisors to conduct construction node work report meetings every week to summarize the progress of the project, analyze construction crux points, and find ways to guarantee the project. building. In view of the construction difficulties caused by rain during the project construction process, all participating units prepared relevant drainage equipment in advance at the request of the project department, and fully drained water during the raining process, striving to restore the construction conditions in the shortest time after the rain stopped. At the same time, under the premise of ensuring safety and quality, the construction shall not be less than 20 hours a day to ensure the safe and efficient progress of the project.
Coordinating on-site and promoting project construction
The sound of piling resounded through the sky, and on the shore of the Yellow Sea, a super factory of components was rising. Under the guidance of Tongwei's efficient management, with the full support of the local government and all participating units, the Tongwei Module Yancheng Project will forge ahead and create a new Yancheng Speed and Tongwei Speed to promote global energy transformation and carbon neutral goals Realize and provide more Tongwei high-efficiency module products. Editor / Zhao E