Central enterprises
The Chaoshan Ring Expressway Rongjiang Bridge was successfully closed
Seetao 2020-08-14 15:47
  • The Rongjiang Bridge has a total length of 4840 meters and a bridge deck width of 33.5 meters. It is designed as two-way six lanes
Reading this article requires
6 Minute

On August 13, 2020, China Communications Construction announced that the main bridge of the Rongjiang Bridge, the largest controlled project of Guangdong Chaoshan Ring Expressway, designed by the Public Planning Institute and constructed by the Second Public Bureau, was successfully closed on the 10th, laying the foundation for the bridge to open to traffic at the end.

The Rongjiang Bridge is a controlled project of the Chaoshan Ring Highway project. The total length of the bridge is 4840 meters, the bridge deck width is 33.5 meters, and the design speed is 100 kilometers per hour. It is designed as a two-way six-lane road. The south bank of Rongjiang River on the east side of Xihu Town, Chaoyang District, City. The bridge is divided into a conventional approach bridge on the north bank of the Rongjiang River, a bridge across the levee on the north bank, a main bridge on the Rongjiang River, and a conventional approach bridge on the south bank of the Rongjiang River. The main bridge is a cable-stayed bridge with double towers and double cable planes with a span of 400 meters.

There are a total of 63 steel box beams in the whole bridge, and the heaviest beam section is 340 tons. In order to successfully install this "big guy", the project has successively solved the problems of large-tonnage steel structure slippage and side span steel box girder variable-amplitude span pier construction through technical research. At the same time, the use of intelligent equipment such as steel box girder and plate unit robot welding, steel box girder segment automatic submerged arc welding machine, etc., controlled the beam section welding time within 50 hours, and finally successfully saved more than 30 days of construction period, ensuring that the typhoon The closure was achieved before. This time the main bridge closure was hoisted by a single-sided deck crane with the accuracy controlled within 5 mm.

After the Chaoshan Ring Expressway is completed and opened to traffic, it will connect the three cities of Chaoshan, pass through the four districts of Jinping, Chenghai, Chaoyang, and Chaonan within our city, and connect Shenshan East, Shanzhan, Yongguan, Shankun and Shanfen Expressways, etc. 5 expressways, connecting three national highways and several provincial highways, forming a multi-ring high-speed network centered on Shantou, and a fast track connecting the three cities of Chaoshan to regional transportation hubs such as ports, airports, high-speed railway stations, and further optimizing the expressways in eastern Guangdong The network layout is of great significance to promoting the integration of Shan Chao Chao and the development of the metropolitan area. Editor/Peng Xue

Comment

Related articles

Central enterprises

The 12th Hydropower Bureau and the Zhejiang Emergency Department build a rescue alliance

08-19

Central enterprises

XCMG Group and Rio Tinto Group sign a global cooperation framework agreement

08-15

Central enterprises

China Power Construction and State power Investment leaders to deepen energy cooperation

07-20

Central enterprises

China Construction Third Engineering Bureau Zhejiang Transportation Project

07-18

Central enterprises

5.635 billion yuan! China Energy Construction won the bid for Jinneng Phase III project

07-15

Central enterprises

National Railway Administration and Chongqing City Sign Cooperation Agreement

07-04

Collect
Comment
Share

Retrieve password

Get verification code
Sure