Spring and Jingming, all things are facing the sun. The builders of Beijing Urban Construction Group worked stubbornly to live up to the brilliance, complete each construction node with high quality, and work hard to pour out the joint growth of each building. The good news continues!
Ice Ribbon "First Show"
As the only newly-built ice competition venue in the Beijing competition area of the Beijing Winter Olympics, the National Speed Skating Stadium "Ice Ribbon" constructed by Beijing Urban Construction Group will host the Beijing Winter Olympics speed skating competition. At 11 o'clock in the morning on April 7, 2021, with the firing of the starting gun, the "Meet in Beijing" ice event test event speed skating competition kicked off at the National Speed Skating Hall "Ice Ribbon", which marked the start of speed skating at the National Speed Skating Hall. The "first show" of the game.
The steel structure construction of the East Hall of the Capital Museum begins
A few days ago, the first steel column on the roof of the main building of the Capital Museum East Building constructed by the General Contracting Department of the Capital Museum was slowly hoisted and placed in place smoothly. So far, the hoisting of the first steel column of the main structural roof of the Capital Museum East Building Project has achieved complete success, marking that the Capital Museum East Building Project has gradually moved from the concrete construction stage to the steel structure construction stage.
The total construction area of the East Hall of the Capital Museum is 99,700 square meters, the contract cost is 1.426 billion yuan, and the engineering steel structure consumption is about 10,000 tons. Since the start of construction, the project has overcome many adverse effects such as tight construction schedules, extreme weather, and the new crown epidemic. The first section of the main concrete structure was capped on January 25 this year, and the steel structure of the main roof was successfully inserted into the main roof steel structure hoisting on March 30 this year. "In the next stage, we will use a high sense of political responsibility and historical mission to ensure that the construction tasks are completed on time with high quality and efficiency, and contribute to the construction of the city's sub-center." The project leader said.
The structure of Gaoloujin Station of Beijing Metro Line 7 is topped
Recently, the main structure of the main structure of the integrated project of the Beijing Metro Line 7 Dongyan 03 High Building Gold Station completed the last section of the roof pouring, and the node target was completed 2 days in advance. The full line of Wansheng South Street Road and Beijing Global Theme Park will be opened to traffic at the end of April. The wonderful appearance lays a solid foundation.
The high-rise golden station integration project is located on the south side of the station and the east side of the C entrance and exit sinking plaza. The project department overcame the impact of the epidemic and continued construction during the Spring Festival, completing 80,000 square meters of earthwork, more than 5,000 tons of steel tying and 23,000 square meters of concrete pouring within 46 days. After the project is topped, the project department will continue to fully complete the key project of the city's sub-center-the east extension of Beijing Rail Transit Line 7 (Wansheng South Street) road construction. At present, the main road has been successfully opened to traffic, and construction of auxiliary roads is underway.
Yizhuang Water Plant "Kunpeng Spreading Wings"
In the Yizhuang Economic Development Zone, Daxing District, a new large-scale water plant is being erected. The main steel structure of the large mechanical mixing clarification tank of this water plant has six decorative steel trusses on the upper eaves, and the shape is like a flying Kunpeng.
At the end of March, the first phase of the Yizhuang Water Plant project—the decorative truss and inter-column support project of the mechanical mixing clarification tank, undertaken by the Urban Construction Jinggong Steel Structure Company, completed the last decorative truss hoisting. The project officially entered the construction site in December 2020. During the peak period of construction, multiple 130-ton cranes and 6 crankshafts were operated at the same time. All employees overcame various disadvantages and completed the construction on schedule while ensuring safety and quality.
The first box girder pouring of the main span of the Gaoan Hualin Bridge is completed
In the early morning of March 31, it lasted 20 hours. In the wind and rain, the Jiangxi Gaoan series of engineering Hualin Bridge project constructed by the General Contracting Department of Construction Engineering successfully completed the casting of the box girder concrete in the first construction section of the third joint on the left, marking The construction of the Hualin Bridge has entered the most critical and difficult construction stage of the main span in the water.
After the successful completion of the first box girder pouring of the main span in the water, the Hualin Bridge project will continue with the concrete pouring of the fifth joint left rear slab and the third joint right first construction section. The construction team will go all out to organize construction in accordance with the schedule for the completion of the main body of the bridge on May 30 to ensure that the Hualin Bridge achieves a safe fall before the Jinjiang flood season.
The structure of Fenghuangshan Station on Shaoxing Metro Line 1 is topped
Recently, with the completion of the concrete pouring of the last car, the rail construction company Shaoxing Metro Line 1 12 bidding Fenghuangshan Station realized the topping of the main structure 7 days earlier than the original plan.
Fenghuangshan Station is an underground two-story island station with open-cut construction. The total length of the station is 467 meters, the standard section is 19.7 meters wide, and the depth is about 16.34 meters to 17.2 meters. Since the earth excavation started on October 3, 2020 to the smooth roofing at the end of March 2021, the project took less than 6 months. The construction speed and quality have been affirmed by the owner, which not only promoted the urban construction brand, but also encouraged the morale of all employees. A solid foundation was laid for accomplishing the goal.
Daxing's largest collective land rental housing project is fully capped
Recently, the collective leasing housing project in Xiyi Village, Yinghai Town, Daxing District, Beijing, undertaken by a company, completed the main structure and fully capped the main structure, marking the official transition of the project to the decoration stage. This is the largest mid-to-high-end long-term rental community in Daxing District. The use has taken a crucial step.
The collective rental housing project of Xiyi Village, Yinghai Town, Daxing District, is located in Yingchang Street, Daxing District, with a total construction area of more than 200,000 square meters, including 20 main buildings, 13 supporting houses and underground garages. The project is constructed as a mid-to-high-end long-term rental community The goal is to provide more than 3000 sets of rental housing after completion. At present, all the builders are making every effort to ensure the orderly and efficient progress of the project, and forge ahead towards the goal of full completion by the end of September this year.
"Hot" construction of Sanya Hongtang Bay Tourism Resort Project
Sanya was already a bit hot in April, and the construction site of the C-05 plot of the Sixth Company Hongtang Bay Tourism Resort was also in full swing. Various large-scale machinery shuttled around the site, roaring one after another, and workers sweating like rain. The eye-catching language of the construction site layout, the neat and uniform signs, and the flying colorful flags not only add vitality to the project, but also inspire the enthusiasm of the builders.
The Hongtang Bay Tourist Resort Project is located on the east side of Hongtang Village, Sanya City. It is the core location of Hongtang Bay in the western sea area. Six companies are responsible for the construction of the third bid section, with a construction area of 53351.24 square meters, including 8 residential buildings and underground garages. At present, the main underground structure of the east and west areas of the C-05 plot of Sanya Hongtang Bay Tourism Resort has entered the sprint and finishing stage, and it is expected that all construction will be completed by the end of April. Editor/Sang Xiaomei